Passed House Re-checks Congress.gov for new actions and updates the bill's status, and fills in any sponsors, committees, or related bills that are missing. It does not re-pull sponsors/cosponsors/committees/related — those rarely change — and it skips all work if nothing has changed upstream, so it's cheap to click.

High-Capacity Grid Act

Introduced Dec 11, 2025

Latest action (Sep 16, 2026) Received in the Senate and Read twice and referred to the Committee on Energy and Natural Resources.

Summary

  • Defines "best-available transmission conductor" as a conductor that provides maximum commercially available energy-carrying capacity, electrical efficiency, and thermal sag mitigation at a given voltage level.
  • Establishes a presumption that using best-available transmission conductors for covered transmission projects is prudent and that associated costs are just and reasonable for rate recovery purposes.
  • Establishes a presumption that using transmission conductors other than best-available conductors is not prudent and that associated costs are not just and reasonable for rate recovery purposes.
  • Applies to new transmission construction and to modifications, upgrades, replacements, or reconductoring of existing transmission lines under Federal Energy Regulatory Commission jurisdiction.
  • Requires the FERC to establish a methodology within 180 days to determine whether a conductor is a best-available transmission conductor and to periodically review and update the methodology.

AI-generated plain-language summary of the bill text — neutral, and may be imperfect. See the full text below for the exact wording.

Sponsor (1)

Money behind the sponsor

Top reported contributors to Julie Fedorchak’s campaign committee (2024 cycle) — who funds the bill’s sponsor, not a claim about this bill. Data from FEC.

  • Employer not reported $161,537
  • STATE OF NORTH DAKOTA $28,930
  • STATE OF ND $17,900
  • THAT'S THE DREAM FARM $13,200
  • BRANDT HOLDINGS $12,400

Organizations whose employees gave the most — itemized individual contributions grouped by the donor’s reported employer (FEC Schedule A). Full finance for Julie Fedorchak → · Outside spending →

Actions (17)

  1. Sep 16, 2026 Received in the Senate and Read twice and referred to the Committee on Energy and Natural Resources. · senate
  2. Sep 15, 2026 Motion to reconsider laid on the table Agreed to without objection. · house
  3. Sep 15, 2026 On motion to suspend the rules and pass the bill, as amended Agreed to by voice vote. (text: CR H5662) · house
  4. Sep 15, 2026 Passed/agreed to in House: On motion to suspend the rules and pass the bill, as amended Agreed to by voice vote.
  5. Sep 15, 2026 DEBATE - The House proceeded with forty minutes of debate on H.R. 6633. · house
  6. Sep 15, 2026 Considered under suspension of the rules. (consideration: CR H5662-5663) · house
  7. Sep 15, 2026 Mr. Guthrie moved to suspend the rules and pass the bill, as amended. · house
  8. Sep 14, 2026 Placed on the Union Calendar, Calendar No. 723. · house
  9. Sep 14, 2026 Reported (Amended) by the Committee on Energy and Commerce. H. Rept. 119-824. · house
  10. Jul 21, 2026 Ordered to be Reported (Amended) by the Yeas and Nays: 49 - 0. · house
  11. Jul 21, 2026 Committee Consideration and Mark-up Session Held · house
  12. Jul 20, 2026 Committee Consideration and Mark-up Session Held · house
  13. Jun 24, 2026 Forwarded by Subcommittee to Full Committee (Amended) by Voice Vote. · house
  14. Jun 24, 2026 Subcommittee Consideration and Mark-up Session Held · house
  15. Dec 11, 2025 Referred to the House Committee on Energy and Commerce. · house
  16. Dec 11, 2025 Referred to the Subcommittee on Energy. · house
  17. Dec 11, 2025 Introduced in House

More bills on these subjects (8)

Other bills that carry the most legislative subjects in common with this one (topical discovery — distinct from the procedural related bills above).

Similar bills (6)

Bills with similar text or summary — includes reintroductions across Congresses. Ranked by semantic similarity of the bill text (computed locally); a neutral discovery aid, not a claim the bills are duplicates.

Text versions (4)

  • Referred in Senate · Sep 16, 2026
  • Engrossed in House · Sep 15, 2026
  • Reported in House · Sep 14, 2026
  • Introduced in House · Dec 11, 2025

Committee action

What happened to this bill in committee — the meetings where it was considered and every recorded vote taken on it.

Meetings where this bill was on the agenda

Full text

AN ACT

To establish a best-available transmission conductor standard for certain transmission projects under the Federal Power Act and to provide for presumptions regarding cost recovery for such conductors.

Be it enacted by the Senate and House of Representatives of the United States of America in Congress assembled,

SECTION 1. SHORT TITLE.

This Act may be cited as the “High-Capacity Grid Act”.

SEC. 2. BEST-AVAILABLE TRANSMISSION CONDUCTOR CLASS.

The Federal Power Act is amended by inserting after section 223 (16 U.S.C. 824w) the following:

“SEC. 224. USE OF BEST-AVAILABLE TRANSMISSION CONDUCTORS.

“(a) Use of Best-available Transmission Conductors.—In exercising its authority under sections 205 and 206, the Commission shall require that public utilities use transmission conductors that are designated as part of the best-available transmission conductor class when carrying out covered projects.

“(b) Regulations.—

“(1) In general.—Not later than 1 year after the date of enactment of this section, the Commission shall issue regulations to carry out this section.

“(2) Inclusions.—In issuing regulations under paragraph

(1), the Commission shall—

“(A) establish, in consultation with the Secretary of Energy, a methodology to designate, as part of the best-available transmission conductors class, transmission conductors that—

“(i) provide the greatest feasible and commercially available energy-carrying capacity at a given voltage level;

“(ii) provide the highest feasible and commercially available electrical efficiency at that voltage level; and

“(iii) provide the greatest feasible and commercially available level of mechanical performance, taking into account relevant factors, including reliability, safety, and affordability;

“(B) using such methodology, designate transmission conductors as part of the best-available transmission conductor class;

“(C) establish filing requirements for public utilities to demonstrate compliance with the regulations, including (as applicable) such information and data the Commission determines necessary to demonstrate project-specific impacts described in subparagraph (D); and

“(D) provide that the requirement to use transmission conductors that are designated as part of the best-available transmission conductor class not apply—

“(i) to carrying out any covered project for which a public utility, prior to the date of enactment of this section, has—

“(I) filed for any State or Federal permit required to carry out the covered project; or

“(II) procured any transmission conductors;

“(ii) to the emergency replacement or repair of transmission facilities necessary to restore service following a natural disaster, act of terrorism, or other event designated as an emergency by a relevant Federal or State authority;

“(iii) if such use would negatively impact safety or violate a reliability standard; or

“(iv) if the public utility carrying out the covered project demonstrates such use would significantly increase the cost per kilowatt- hour of electricity without providing a material and commensurate increase to capacity, efficiency, or mechanical performance.

“(c) Periodic Review and Updates.—The Commission may, to reflect improvements in technology, periodically review and update—

“(1) the methodology for designating transmission conductors as part of the best-available transmission conductor class; and

“(2) the designation of transmission conductors as part of the best-available transmission conductor class.

“(d) Definitions.—In this section:

“(1) Best-available transmission conductor class.—The term ‘best-available transmission conductor class’ means a class of transmission conductors that are designated as part of the class pursuant to this section.

“(2) Commission.—The term ‘Commission’ means the Federal Energy Regulatory Commission.

“(3) Covered project.—The term ‘covered project’ means—

“(A) the construction of a new transmission facility subject to the jurisdiction of the Commission under section 201(b) that includes a transmission conductor; or

“(B) any major (as determined by the Commission) modification, upgrade, replacement, or reconductoring of an existing transmission conductor subject to such jurisdiction.

“(4) Reliability standard.—The term ‘reliability standard’ has the meaning given such term in section 215.”.

Passed the House of Representatives September 15, 2026.

Attest:

Clerk. 119th CONGRESS

2d Session

H. R. 6633

AN ACT

To establish a best-available transmission conductor standard for certain transmission projects under the Federal Power Act and to provide for presumptions regarding cost recovery for such conductors.