S 8114 NY
Relates to the siting of new electric transmission lines
A state bill is a proposed law in a state legislature — separate from the U.S. Congress. Learn more →
Summary
Provides that in the siting of new electric transmission facilities, including high-voltage transmission lines, the following corridors shall be utilized in the following order of priority in accordance with feasibility of economic and engineering considerations, reliability of the electric system and the protection of the environment: existing utility corridors; highway (interstate, freeway and state trunk) and railroad corridors; recreational trails, to the extent that the facilities may be constructed below ground and that the facilities do not significantly impact environmentally sensitive areas; and new corridors; provides that the commissioner of transportation shall engage in coordination activities with a utility or transmission line developer to review requested highway corridors for possible permitted locations of transmission lines.
Sponsor (1)
- Jeremy Cooney Democratic · primary
Action history (4)
- May 15, 2025 REFERRED TO ENERGY AND TELECOMMUNICATIONS · upper
- Jan 7, 2026 REFERRED TO ENERGY AND TELECOMMUNICATIONS · upper
- Apr 30, 2026 AMEND AND RECOMMIT TO ENERGY AND TELECOMMUNICATIONS · upper
- Apr 30, 2026 PRINT NUMBER 8114A · upper
Text versions (3)
Full text
Full text imported from assembly.state.ny.us
Skip to main content
New York State Assembly Speaker Carl E. Heastie
--> --> -->
Assembly Members
Legislative Info
Public Hearings
Speaker's Press
Assembly Reports
Committees & More
Bill Search Home Laws Legislative Calendar Public Hearing Schedule Assembly Calendars Assembly Committee Agenda Javascript must be enabled to properly view this page.
Bill No.: Summary Actions Committee Votes Floor Votes Memo Text LFIN Chamber Video/Transcript S08114 Summary: BILL NO S08114A   SAME AS No Same As   SPONSOR COONEY   COSPNSR   MLTSPNSR   Amd §141, Pub Serv L; amd §40, Hway L   Provides that in the siting of new electric transmission facilities, including high-voltage transmission lines, the following corridors shall be utilized in the following order of priority in accordance with feasibility of economic and engineering considerations, reliability of the electric system and the protection of the environment: existing utility corridors; highway (interstate, freeway and state trunk) and railroad corridors; recreational trails, to the extent that the facilities may be constructed below ground and that the facilities do not significantly impact environmentally sensitive areas; and new corridors; provides that the commissioner of transportation shall engage in coordination activities with a utility or transmission line developer to review requested highway corridors for possible permitted locations of transmission lines.
Go to top S08114 Text:
STATE OF NEW YORK ________________________________________________________________________
8114--A
2025-2026 Regular Sessions
IN SENATE
May 15, 2025 ___________
Introduced by Sen. COONEY -- read twice and ordered printed, and when printed to be committed to the Committee on Energy and Telecommuni- cations -- recommitted to the Committee on Energy and Telecommuni- cations in accordance with Senate Rule 6, sec. 8 -- committee discharged, bill amended, ordered reprinted as amended and recommitted to said committee
AN ACT to amend the public service law and the highway law, in relation to the siting of new electric transmission facilities
The People of the State of New York, represented in Senate and Assem- bly, do enact as follows:
1 Section 1. Section 141 of the public service law is amended by adding 2 a new subdivision 7 to read as follows: 3 7. (a) In the siting of new electric transmission facilities, includ- 4 ing high-voltage transmission lines, the following corridors shall be 5 utilized in the following order of priority in accordance with feasibil- 6 ity of economic and engineering considerations, reliability of the elec- 7 tric system and the protection of the environment: 8 (i) Existing utility corridors; provided that any such existing utili- 9 ty corridors shall be made available, with just compensation, reasonable 10 terms and conditions, and due process overseen by the department, on a 11 nondiscriminatory and ongoing basis, to any entity selected to build, 12 own, and operate bulk electric power facilities pursuant to planning 13 processes established by the federally designated electric bulk system 14 operator or any New York state-sponsored transmission procurement proc- 15 ess, regardless of whether such selected entity is an incumbent operator 16 with existing interest in any such existing utility corridor; 17 (ii) Highway (interstate, freeway and state trunk) and railroad corri- 18 dors; 19 (iii) Recreational trails, to the extent that the facilities may be 20 constructed below ground and that the facilities do not significantly 21 impact environmentally sensitive areas; and 22 (iv) New corridors. 23 (b) (i) High-voltage transmission lines, pursuant to the laws of this 24 state or the ordinance of any city or county, may be constructed,
EXPLANATION--Matter in italics (underscored) is new; matter in brackets [ ] is old law to be omitted. LBD13020-04-6
S. 8114--A 2
1 placed, or maintained across any public right of way or along any trunk 2 highway, federally-aided state trunk highway, controlled access highway, 3 interstate highway, or roadway, except as deemed necessary by the 4 commissioner of transportation to protect public safety or ensure the 5 proper function of such trunk highway. 6 (ii) If the commissioner of transportation denies a high-voltage elec- 7 tric line collocation request, the reasons for the denial shall be 8 submitted for review to the chairs and ranking minority members of the 9 senate and assembly committees with jurisdiction over energy and trans- 10 portation, the chair of the public service commission, and the commis- 11 sioner of economic development within ninety days of such denial. 12 § 2. Section 40 of the highway law, as amended by chapter 1110 of the 13 laws of 1971, is amended to read as follows: 14 § 40. Authority of commissioner of transportation with respect to the 15 performance of contracts for construction, reconstruction or improvement 16 of state highways, highway projects under the supervision of the depart- 17 ment of transportation, bridges, grade crossing eliminations and stream 18 channel improvements; completion of work by surety; cancellation of 19 contract by the commissioner [ of transportation ]. 1. The performance of 20 every contract for the construction, reconstruction or improvement of a 21 state highway, bridge, grade crossing elimination or stream channel 22 improvement shall be under the supervision and control of the commis- 23 sioner [ of transportation ], and it shall be [ his ] such commissioner's 24 duty to see that every such contract is performed in accordance with the 25 provisions of the contract and with the plans and specifications forming 26 a part thereof. If the commissioner [ of transportation ] shall determine 27 that the work upon any contract for the construction, improvement, main- 28 tenance, repair or reconstruction, of a state highway, other highway 29 under the supervision of the department [ of transportation ], bridge, 30 grade crossing elimination or stream channel improvement, is not being 31 performed according to the contract or for the best interest of the 32 state, the execution of the work by the contractor may be temporarily 33 suspended by [ the ] such commissioner [ of transportation ], who may then 34 proceed with the work under [ his ] their own direction in such manner as 35 will accord with the contract specifications and be for the best inter- 36 ests of the state; or [ he ] such commissioner may terminate the contrac- 37 tor's employment under the contract while it is in progress, and there- 38 upon, proceed with the work, in affirmance of the contract, by contract 39 negotiated or publicly let, by the use of [ his ] their own forces, by 40 calling upon the surety to complete the work in accordance with the 41 plans and specifications or by a combination of any such methods; or 42 [ he ] their may cancel the contract and either readvertise and relet as 43 provided in section thirty-eight of this [ chapter ] article , or complete 44 the work under [ his ] their own direction in such manner as will accord 45 with the contract specifications and be for the best interests of the 46 state. Any excess in the cost of completing the contract beyond the 47 price for which it was originally awarded shall be charged to and paid 48 by the contractor failing to perform the work or [ his ] such contractor's 49 surety. Where the estimate for the completion of a cancelled contract 50 or defaulted contract, or a contract being completed pursuant to the 51 provisions of this section, is in excess of the balance of the amount 52 originally set aside by the state to provide for the construction, 53 reconstruction, improvement, maintenance or repair of such highway, or 54 other construction project, together with any amount appropriated by the 55 county, town or village for such improvement, the commissioner [ of 56 transportation ] is authorized to set aside from any funds available for
S. 8114--A 3
1 the construction or reconstruction of state highways, highway projects 2 under the supervision of the department [ of transportation ], bridges, 3 grade crossing eliminations and stream channel improvements, an addi- 4 tional sum equal to such excess including the proportionate share of the 5 county, town or village; and to pay such excess in the first instance, 6 including the share of the county, town or village, pending recovery of 7 excess cost from the defaulting contractor or [ his ] such contractor's 8 surety, as provided in this section. In the event that the state fails 9 to recover from the defaulting contractor or surety the excess cost in 10 completing the contract over the amount for which it was originally 11 awarded, the county, town, or village shall pay to the state upon the 12 demand of the commissioner [ of transportation ] the same proportion of 13 such excess cost as was originally appropriated by the county, town or 14 village, for the improvement, and the board of supervisors, town board 15 or village trustees shall be subject to mandamus proceedings by the 16 attorney general to enforce the payment of the share of the county, town 17 or village of such excess cost. Every contract for the construction, 18 improvement, maintenance, repair or reconstruction of a state highway, 19 highway project under the supervision of the department [ of transporta- 20 tion ], bridge, grade crossing elimination or stream channel improvement, 21 shall reserve to the commissioner [ of transportation ] the right to 22 suspend or cancel the contract as above provided, and to complete the 23 work thereunder by contract negotiated or publicly let or by the use of 24 [ his ] their own forces, or affirm the contract and thereupon to complete 25 the work thereunder according to any of the methods above provided as 26 the commissioner [ of transportation ] may determine. 27 2. Upon written request, the commissioner shall engage in coordination 28 activities with a utility or transmission line developer to review 29 requested highway corridors for possible permitted locations of trans- 30 mission lines. A project coordinator shall be assigned within thirty 31 days of the written request. The department shall share all known plans 32 with utilities on potential future projects that could impact the place- 33 ment of a high-voltage transmission line. 34 3. (a) When a permittable route along a highway corridor has been 35 identified by the department and the utility or developer, the depart- 36 ment shall engage in consultation with the utility or developer to 37 develop a "constructability report" to be utilized by both parties when 38 co-location projects are being planned and approved. The report shall be 39 approved by both parties prior to the department issuing a permit for 40 use of the highway right-of-way. 41 (b) A constructability report shall be prepared by the utility in 42 consultation with the department and shall include the terms and condi- 43 tions for building the co-location project. Included within such report 44 shall be an agreed upon timeframe for which there will not be any 45 request by the department for relocation of the transmission line. If 46 the department needs a transmission line in its right-of-way relocated, 47 it shall give the utility a ten-year advance notice. Should the depart- 48 ment require the relocation of a transmission line sooner than what is 49 agreed upon, and/or gives less than a ten-year notice of relocation, 50 then the department shall be responsible for seventy-five percent of the 51 re-location costs. 52 § 3. This act shall take effect on the ninetieth day after it shall 53 have become a law; provided, however, that the amendments to section 141 54 of the public service law made by section one of this act shall not 55 affect the repeal of such section and shall be deemed repealed there- 56 with.
Go to top