HR 6983 Introduced Re-checks Congress.gov for new actions and updates the bill's status, and fills in any sponsors, committees, or related bills that are missing. It does not re-pull sponsors/cosponsors/committees/related — those rarely change — and it skips all work if nothing has changed upstream, so it's cheap to click.
To require data centers to generate electricity, and for other purposes.
Summary
- Requires all U.S. data centers that consume at least 50 megawatts per day to generate all of their annual electricity consumption on-site.
- Requires that at least 75 percent of electricity generated by data centers be from clean energy sources beginning January 1, 2035.
- Requires 100 percent of electricity generated by data centers to be from clean energy sources beginning January 1, 2040.
- Establishes civil penalties of up to $100,000 per day for violations until rectified.
- Requires the Secretary of Energy to establish an administrative process for issuing penalties within 30 days of enactment.
AI-generated plain-language summary of the bill text — neutral, and may be imperfect. See the full text below for the exact wording.
Sponsor (1)
-
Rep. Menendez, Robert (D-NJ) [#8]
4 cosponsors
-
Rep. Casar, Greg (D-TX) [#35] -
Rep. Grijalva, Adelita S. (D-AZ) [#7] -
Rep. Larson, John B. (D-CT) [#1] -
Rep. Velázquez, Nydia M. (D-NY) [#7]
Actions (2)
- Jan 8, 2026 Referred to the House Committee on Energy and Commerce. · house
- Jan 8, 2026 Introduced in House
Text versions (1)
Bills are re-published as they move (Introduced → Reported → Engrossed → Enrolled …). Each stage below is a separate text; pick two to see what changed. Data from Congress.gov.
Full text
IN THE HOUSE OF REPRESENTATIVES
January 8, 2026
Mr. Menendez (for himself and Mr. Casar) introduced the following bill; which was referred to the Committee on Energy and Commerce
A BILL
To require data centers to generate electricity, and for other purposes.
Be it enacted by the Senate and House of Representatives of the United States of America in Congress assembled,
SECTION 1. SHORT TITLE.
This Act may be cited as the “Preventing Rate Inflation in Consumer Energy Act” or the “PRICE Act”.
SEC. 2. REQUIREMENT FOR DATA CENTERS TO GENERATE ELECTRICITY.
(a) Requirement.—Each data center located in the United States shall generate all of the electricity the data center consumes each year.
(b) Use of Clean Energy Sources.—
(1) 75 percent.—During the period beginning on January 1, 2035, and ending on the date described in paragraph (2), not less than 75 percent of the electricity generated by a data center for purposes of subsection (a) shall be from a clean energy source.
(2) 100 percent.—Beginning on January 1, 2040, 100 percent of the electricity generated by a data center for purposes of subsection (a) shall be from a clean energy source.
(c) Enforcement.—
(1) Civil penalty.—Any data center that violates any provision of this section shall be subject to a civil penalty of not more than $100,000 per day until the violation is rectified.
(2) Establishment of administrative process.—Not later than 30 days after the date of enactment of this Act, the Secretary of Energy shall establish an administrative process for the issuance of civil penalties for violations of this section.
(d) Definitions.—In this section:
(1) Clean energy source.—The term “clean energy source” includes a solar, wind, battery, green hydrogen, hydropower, and geothermal source.
(2) Data center.—The term “data center” means a facility that—
(A) is described in section 453(a)(1) of the Energy Independence and Security Act of 2007 (42 U.S.C. 17112(a)(1)); and
(B) consumes at least 50 megawatts each day. <all>